Westross Road

Project Description
Project limits: Westross Road from Hydro Bay Road to Zion Line
Surface: Double Surface Treatment
Scope: Culvert replacements and new granular material

Schedule

Township staff have replaced half of the culverts that are due for replacement earlier this summer and will continue to replace the remain culverts on September 14th.  At the same time the existing double surface treatment will be removed, and new granular material will be added.
Greenwood Paving is schedule to install the double surface treatment during the week of October 4th.

Status

Under Construction

Notices

September 13, 2021

Funding

Council of the Township of Whitewater Region has funded the construction of Westross Road through Gas Tax.