Project Description
The project limits of the Government Road reconstruction project are between Foresters Falls Road (County Road 7) and Fletcher Road.
The 3.0 km reconstruction project scope of work consists of the following:
Status
Tender Stage
Schedule
The geotechnical investigation, including 18 completed boreholes, is complete. The project has moved into the tender phase, which closes at the end of March.
Notices
Future notices will be sent to property owners in the project area.
Funding
The 2026 budget includes the reconstruction of Government Road, funded by the Ontario Community Infrastructure Fund (OCIF), Canada Community-Building Fund (CCBF), and taxation. The total project cost for the Government Road reconstruction project is estimated at $660,000.
Map

Project Contact
Lane Cleroux
Manager of Public Works
Township of Whitewater Region
613-646-2282 ext. 128
lcleroux@whitewaterregion.ca