Kohlsmith Road

Project Description

The project limits consist of Kohlsmith Road from Kerr Line to Queens Line (CR-4). 

The 2.8 km rehabilitation project scope of work consists of the following:

  • Removal of double surface treatment surface
  • Brushing
  • Culvert replacement
  • Minor ditching
  • New granular base material
  • Installation of new a double surface treatment.

Status

Design Phase

Schedule

The removal of the existing double surface treatment will take place at the end of May. Replacement of culverts, ditching, granular base and double treatment surface is scheduled to start in June and be completed in July. 

Notices

Future notices will be sent to property owners along the project area.

Funding

The Council of the Township of Whitewater Region has included the rehabilitation of Kohlsmith Road in the 2024 budget, funded by the Ontario Community Infrastructure Fund (OCIF) and Canada Community Building Fund (CCBF).

Map

Map of Kohlsmith Road

Project Contact

Kyle Eady
Road Superintendent
Township of Whitewater Region
613-646-2282 ext. 152
keady@whitewaterregion.ca